How to choose a cleanroom contractor in Malaysia

Most cleanroom disputes start in the scope document, not on site.

REGISTRATION

Check CIDB registration first

Construction works in Malaysia require registration with CIDB under Act 520. Ask for the registration number, the grade and the category. Then check two things: that the grade covers your contract value, and that the category covers mechanical and electrical work rather than building works alone. Learn more about classification requirements.

SCOPE

Get the scope split in writing

Every cleanroom project has several parties in it. Name them before anyone prices anything. See how we structure scope.

  • Who supplies the wall and ceiling systems
  • Who does the air handling and the electrical work
  • Who arranges classification testing
  • Who handles fire authority and local council submissions
  • Who owns the documentation pack at the end
QUESTIONS

Five questions worth asking early

  1. Which grade and category is your CIDB registration, and does it cover this contract value?
  2. What air change rate are you designing to, and what does that assume about my heat load?
  3. Who carries out the classification testing, and are they independent of you?
  4. What happens if the room fails its first test, and who pays for the rework?
  5. How do I reach the filters to change them without shutting down production?
TESTING

Do not let the builder certify the build

Classification testing should be carried out by a party with no interest in the result. If one company designs the room, installs it, and then signs off that it passes, your auditor will notice before you do. Learn about validation support.

RED FLAGS

What should make you slow down

  • A price per square foot quoted before anyone has seen the site. What actually drives cost.
  • No air change rate stated anywhere in the proposal
  • Testing and certification bundled in with the build, by the same party
  • A scope document that does not say who submits to the fire authority

NEXT STEP

Tell us the classification you need.

Send your floor area, target ISO class and process. We reply with a scope outline and an indicative range.